Bored piles by means of the Vor der Wand method
Aarsleff Ground Engineering has bored 29 piles for the construction of the new upper secondary school in Viborg. Due to a deep-lying sewer pipe, it was not possible to establish seven new spread foundations directly. So the spread foundation loads were led under the pipe to avoid damaging the pipe.
Work done by Aarsleff Construction and Ground Engineering